Project

Dogger Bank Creyke Beck will be the first stage of development in the Dogger Bank Zone. It will have an installed capacity of up to 2.4GW and will connect into the existing Creyke Beck substation near Cottingham, in the East Riding of Yorkshire. It will comprise of two offshore wind farms with an installed capacity of up to 1.2GW each. Those two wind farms are:

Dogger Bank Creyke Beck A located in the southern part of Tranche A, with a size of 515km2 and 131 kilometres from shore at its closest point.

Dogger Bank Creyke Beck B located in the western part of Tranche A, the largest in area with a size of 599km2 and also 131 kilometres from shore at its closest point.